feat(phase-5): implement battery model, charging queues, production deadlines, and safe reassignment

This commit is contained in:
2026-10-21 11:36:48 +05:30
parent 56806079a9
commit 1e50508f53
20 changed files with 2215 additions and 99 deletions
+51 -48
View File
@@ -1,7 +1,7 @@
# Project Status: Warehouse Robot Fleet Digital Twin
**Last Updated**: October 21, 2026
**Current Phase**: **Phase 4: Routing and Fleet Assignment (COMPLETED)**
**Current Phase**: **Phase 5: Charging and Operational Constraints (COMPLETED)**
**Status**: Ready for User Review and Approval
---
@@ -14,58 +14,56 @@
| **Phase 1** | **Warehouse model** | **COMPLETED** | **26 passed** |
| **Phase 2** | **Robot and task models** | **COMPLETED** | **56 passed** |
| **Phase 3** | **Discrete-event simulation** | **COMPLETED** | **72 passed** |
| **Phase 4** | **Routing and fleet assignment** | **COMPLETED** | **95 passed (100%)** |
| Phase 5 | Charging and operational constraints | Planned (Next) | - |
| Phase 6 | Analytics and experiment framework | Planned | - |
| **Phase 4** | **Routing and fleet assignment** | **COMPLETED** | **95 passed** |
| **Phase 5** | **Charging and operational constraints** | **COMPLETED** | **110 passed (100%)** |
| Phase 6 | Analytics and experiment framework | Planned (Next) | - |
| Phase 7 | Omniverse USD visualization | Planned | - |
| Phase 8 | Operational dashboard | Planned | - |
| Phase 9 | Optimization and final demonstration | Planned | - |
---
## 2. Completed Tasks (Phase 4)
## 2. Completed Tasks (Phase 5)
- [x] Implemented NetworkX shortest path planning module (`src/warehouse_twin/routing/path_planner.py`):
- Dijkstra and A* path calculation with distance and traversal time scoring.
- Robot capability and class restrictions (Zone B 4.0m wide aisles restricted to Heavy AMRs).
- Dynamic edge cost calculation incorporating congestion penalties.
- Fail-fast unreachable destination diagnostics (`NoPathFoundError`).
- Unit test suite: 9 passed in `tests/unit/test_path_planner.py`.
- [x] Implemented Time-Space Reservation Grid (`src/warehouse_twin/routing/reservations.py`):
- Temporal reservation of nodes and physical aisle edge segments.
- Head-on collision elimination on shared bidirectional aisles.
- Rear-end / following headway buffer enforcement ($1.0\text{s}$).
- Intersection exclusive zone protection.
- Earliest safe departure search and expired slot cleanup.
- Unit test suite: 7 passed in `tests/unit/test_reservations.py`.
- [x] Implemented Multi-Robot Traffic Manager (`src/warehouse_twin/routing/traffic_manager.py`):
- Priority-aware right-of-way arbitration (Production Feed > Replenishment > Picking).
- Loaded vs. empty yielding rules (`loaded_yields_to_empty: false`).
- Cooperative waypoint waiting on corridor contention (`YIELD_WAIT`).
- Deadlock timeout detection and dynamic bypass rerouting (`REPLAN`).
- Unit test suite: 7 passed in `tests/unit/test_traffic_manager.py`.
- [x] Integrated spatial routing into `SimulationEnvironment` (`src/warehouse_twin/simulation/sim_engine.py`):
- Waypoint-by-waypoint path traversal process replacing instantaneous transit timeouts.
- Telemetry streaming with path lengths, waypoint counts, and yield events.
- Trajectory recording: 3,326 time-stamped points across fleet.
- JSON trajectory export (`results/trajectories/trajectory_sim.json`).
- Unit test suite: 1 passed in `tests/unit/test_trajectory_export.py`.
- [x] Enhanced OpenUSD scene export (`omniverse/scenes/warehouse_phase4.usda`):
- Includes topological navigation highways (cyan/blue) and Zone B wide aisles (amber).
- [x] Updated CLI entry point:
- Added `--output-trajectories` option to `run-sim`.
- Added Phase 4 traffic KPI reporting (conflicts, yields, wait times, reroutes, deadlocks).
- [x] Test Suite: Expanded to **95 passed unit tests (100% pass rate in 0.73s)**.
- [x] Documentation: Created `docs/phases/phase_4_routing_and_fleet_assignment.md`.
- [x] Implemented Physics-Informed Battery Model (`src/warehouse_twin/fleet/battery_model.py`):
- Mode-specific power draw computation (`idle`, `moving_empty`, `moving_loaded`, `handling`).
- Load-dependent consumption model: Linear scaling between empty and loaded draw based on carried payload.
- Complete mission energy feasibility validator: guarantees robots have sufficient battery for empty transit, pick handling, loaded transit, drop handling, and travel to nearest compatible charging bay, while maintaining a strict 20% minimum reserve threshold.
- Charger plug-in and duration calculator factoring in 95% electrical conversion efficiency.
- Unit test suite: 6 passed in `tests/unit/test_battery_model.py`.
- [x] Implemented Capacity-Constrained Charging Queue Manager (`src/warehouse_twin/fleet/charging_manager.py`):
- Wrapped charging bays in SimPy `Resource(capacity=1)` to model physical plug-in bottlenecks and real-world queueing.
- Compatibility-aware station selection ($50\,\text{kW}$ for Heavy AMRs, $25\,\text{kW}$ for Light AMRs) prioritized by shortest queue and Euclidean distance.
- Opportunistic charging triggering ($<40\%$ battery) during idle periods with a minimum charge duration ($180\,\text{s}$) to avoid rapid cycling.
- Comprehensive bay metrics: occupancy rate, active charging duration, queue wait duration, and total energy delivered.
- Unit test suite: 3 passed in `tests/unit/test_charging_manager.py`.
- [x] Implemented Safe Task Reassignment & Preemption (`src/warehouse_twin/fleet/task_reassigner.py`):
- Safely detaches un-started tasks from robots dropping below critical reserve thresholds.
- Releases spatial reservations in `TimeSpaceReservationGrid`, returns tasks to `PENDING`, and re-enqueues for dispatch.
- Preempts un-started low-priority picking tasks when urgent production-line feeder tasks arrive.
- Unit test suite: 2 passed in `tests/unit/test_task_reassignment.py`.
- [x] Implemented Production-Line Delivery Deadlines & Stock-out Tracking:
- Tight SLA tracking for assembly line replenishment tasks with lateness and on-time compliance reporting.
- Real-time inventory depletion checks triggering urgent replenishment upon crossing minimum reorder thresholds.
- Unit test suites: 3 passed in `tests/unit/test_production_deadlines.py`, 1 passed in `tests/unit/test_stockout_and_replenishment.py`.
- [x] Integrated Fleet Charging & Battery System into `SimulationEnvironment` (`src/warehouse_twin/simulation/sim_engine.py`):
- Dynamic battery depletion across all mission legs with load-dependent adjustments.
- Low battery abort logic prior to pick handling to prevent mid-aisle stranding.
- SimPy capacity-constrained charging process with queue wait time metrics.
- Enhanced KPI tracking: energy consumed/charged, bay occupancy, charging wait times, deadline compliance.
- [x] Enhanced OpenUSD scene export (`omniverse/scenes/warehouse_phase5.usda`):
- Updated scene with high-power charging bays, navigation mesh, and fleet visual cues.
- [x] Test Suite: Expanded to **110 passed unit tests (100% pass rate in 0.70s)**.
- [x] Documentation: Created `docs/phases/phase_5_charging_and_operational_constraints.md`.
---
## 3. Test & Validation Summary
- **Total Unit Tests Executed**: 95
- **Passed**: 95
- **Total Unit Tests Executed**: 110
- **Passed**: 110
- **Failed**: 0
- **Execution Time**: ~0.73 seconds
- **Execution Time**: ~0.70 seconds
- **Test Suites**:
- `test_environment.py`: 5 passed
- `test_logging.py`: 3 passed
@@ -80,6 +78,11 @@
- `test_path_planner.py`: 9 passed
- `test_reservations.py`: 7 passed
- `test_traffic_manager.py`: 7 passed
- `test_battery_model.py`: 6 passed
- `test_charging_manager.py`: 3 passed
- `test_production_deadlines.py`: 3 passed
- `test_task_reassignment.py`: 2 passed
- `test_stockout_and_replenishment.py`: 1 passed
- `test_sim_engine.py`: 5 passed
- `test_trajectory_export.py`: 1 passed
@@ -88,19 +91,19 @@
## 4. Benchmark Performance (1-Hour Simulation Run)
- **Simulated Duration**: 3,600.0s (1.00 hour)
- **Wall-clock Execution Time**: ~1.48s
- **Wall-clock Execution Time**: ~2.60s
- **Tasks Created**: 86
- **Tasks Completed**: 85
- **Throughput**: 85.00 tasks/hr
- **Average Turnaround Time**: 91.2s
- **Average Waiting Time**: 29.9s
- **Average Execution Time**: 61.3s
- **On-Time Delivery Rate**: 100.0%
- **On-Time Delivery Rate**: 100.0% (0 deadline violations)
- **Fleet Utilization**: 50.9%
- **Replenishment Triggers**: 1
- **Traffic Conflicts Detected**: 36
- **Yield Waits Executed**: 36
- **Total Yield Wait Time**: 56.0s (avg 1.55s per yield)
- **Total Energy Consumed**: 7.82 kWh
- **Total Energy Charged**: 21.55 kWh (across stress test runs)
- **Charging Sessions**: 4 sessions completed
- **Charging Queue Wait Time**: 0.0s (optimal station capacity)
- **Deadlocks Prevented**: 0 (zero deadlocks occurred)
- **Head-on Collisions**: 0 (100% collision-free)
- **Trajectory Points Recorded**: 3,326
- **Stranded Robots**: 0 (100% mission feasibility validation)